Powered By Blogger

Saturday 18 June 2016

Engineer's Life Now-a-Days


Useful Data for Site Execution (Construction Site) Part-3

Slipform construction is a method for building large towers or bridges from concrete. The name refers to the moving form the concrete is poured into, which moves along the project as the previously poured concrete hardens behind it. The technique has also been applied to road construction.


Vertical Slipform relies on the quick-setting properties of concrete requiring a balance between early strength gain and workability. Concrete needs to be workable enough to be placed to the formwork and strong enough to develop early strength so that the form can slip upwards without any disturbance to the freshly placed concrete.
From foundation to rooftop of even the very tallest projects, with the system’s hydraulic jacks, installing steel reinforcement and pouring concrete become much easier and faster, plus can be more efficiently controlled to assure the highest quality finished cement structure. 
SLIPFORM technology virtually eliminates unnecessary waste and hazards, making this construction system even more efficient and economical.











  • SLIPFORM saves time
  • SLIPFORM saves labor
  • SLIPFORM is safety
  • Friday 17 June 2016

    Useful Data for Site Execution (Construction Site) Part-2

    Following are few general points to remember for civil site engineers to make the construction work easier while maintaining quality of construction.


    • Lapping is not allowed for the bars having diameters more than 36 mm.
    • Chair spacing maximum spacing is 1.00 m (or) 1 No per 1m2.
    • For dowels rod minimum of 12 mm diameter should be used.
    • Chairs minimum of 12 mm diameter bars to be used.
    • Longitudinal reinforcement not less than 0.8% and more than 6% of gross C/S.
    • Minimum bars for square column is 4 No’s and 6 No’s for circular column.
    • Main bars in the slabs shall not be less than 8 mm (HYSD) or 10 mm (Plain bars) and the distributors not less than 8 mm and not more than 1/8 of slab thickness.
    • Minimum thickness of slab is 125 mm.
    • Dimension tolerance for cubes + 2 mm.
    • Free fall of concrete is allowed maximum to 1.50m.
    • Lap slices not be used for bar larger than 36 mm.
    • Water absorption of bricks should not be more than 15 %.
    • PH value of the water should not be less than 6.
    • Compressive strength of Bricks is 3.5 N / mm2.
    • In steel reinforcement binding wire required is 8 kg per MT.
    • In soil filling as per IS code, 3 samples should be taken for core cutting test for every 100m2.

    Density of Materials:


    Material
    Density
    Bricks
    1600 – 1920 kg/m3
    Concrete block
    1920 kg/ m3
    Reinforced concrete
    2310 – 2700 kg/ m3


    Curing time of RCC Members for different types of cement:

    Super Sulphate cement: 7 days
    Ordinary Portland cement OPC: 10 days
    Minerals & Admixture added cement: 14 days

    De-Shuttering time of different RCC Members


    RCC Member
    De-shuttering time
    For columns, walls, vertical form works
    16-24 hrs.
    Soffit formwork to slabs
    3 days (props to be refixed after removal)
    Soffit to beams props
    7 days (props to refixed after removal)
    Beams spanning upto 4.5m
    7 days
    Beams spanning over 4.5m
    14 days
    Arches spanning up to 6m
    14 days
    Arches spanning over 6m
    21 days

    Cube samples required for different quantity of concrete:

    Quantity of Concrete
    No. of cubes required
    1 – 5 m3
    1 No’s
    6 0 15 m3
    2 No’s
    16 – 30 m3
    3 No’s
    31 – 50 m3
    4 No’s
    Above 50 m3
    4 + 1 No’s of addition of each 50 m3



    Monday 13 June 2016

    Useful Data for Site Execution (Construction Site) Part-1 Incl. Types of Equipment use on site and Column layout-Casting

    Site soil Excavation & Foundation:-
    Prior to start of construction work excavation is done at site up to the level required for start
    of construction. To provide access to vehicles construction machineries Ramp is made with
    proper slope.


    Poclain used for excavation


    Dozer used for making Ramp, dumping & spreading soil

    Slope stabilization is done of cutting soil edges by keeping sand bags at slopes & by
    Step cutting so that soil doesn’t collapse during construction stage causing safety Issue.
     Proper drainage arrangement is done to avoid water logging.
     Land around the construction area is levelled for keeping construction material & Machinery



    Tower Boom(Placer Boom)


    Boom is fixed in the tower in position from where it is easy to whole area of tower is accessible.
    · Can pump upto 50 cum/hr. or Depends upon its Power.

    Hydra machine used for column reinforcement Shifting

    Back Hoe loader (JCB)
     Used for excavation where quantity of soil to be excavated is less
     Can also used for various other construction purposes like shifting of material, ground
    dressing & levelling.

    Structural Member Construction Methodology &
    specifications
    1. Column
    Columns are compressive member of a structure. There position in a structure should be such that, they carry the load coming efficiently.



    Activities involve in Column construction

    ü Column Layout
    After casting of raft again the layout of column is done in order to check the actual position of
    Vertical bars of columns. The layout is also helpful to place the shuttering on actual position, so that
    the column should be in proper position according to drawing(Column layout drawing). Column
    Layout is doe according to the Grid line mentioned in coordinated framing plan. Grid line is marked
    Near the column as per drawing.

    Column layout done prior to bar binding work


    Ø Why Column Layout??
    Ø So that column remains in their position decided as per Co-ordinate drawing of Tower.
    Ø Verticality of structure is maintained.
    Ø So that area of particular Flat doesn’t reduce due to dislocation of column from actual
    Assign position.

    ü Bar Binding Work :
    Steel Grade Used: FE 500D
    Dia of bar used : 12mm to 32mm for longitudinal bars & 8mm to 10mm for Tie bars.
    Tie bar hooks are bend up at 45áµ’ as per IS 456









    Coupler/Reducer: vertical joints in case of longitudinal bars of column are provide using
    coupler. Where ever Dia of column is reducing in above floor reducer is used to provide
    joins
    · Used for Bars of Dia 16mm to 32mm
    · Lap length of 36D is provide in case of 12mm Dia bar or bar reducing from 16mm to
    12mm.
    · Thread are provide at ends of bar for couple/reducer.


    Coupler used for joining vertical bar in column.
    Couplers

    Bar binding of column


    Important points For bar binding Of columns :-
    · Lap Zone is H/3 from top & bottom slab.
    · Alternate longitudinal Bar of column should have a length difference of 600mm so that
    vertical reinforcement joint doesn’t come at 1 point as shear concentration point of
    view.
    · Coupler should be properly tightened

    a. Formwork for columns
    The shuttering either conventional or system is fixed around column and plumb of this shuttering
    is checked out. At bottom the T shaped bars keeps the shuttering on position and at top and
    middle cover blocks are fixed so that proper cover could be provide to reinforcement. The T
    shaped bar at bottom and cover blocks at middle and top ensure the straightness of vertical
    Reinforcement.


    Table: Period of removal of formwork


    S. No.
    Description of structural member
    Period of time
    1
    Walls, columns and vertical sides of beams
    16-24 Hours


    It should be strong enough to withstand all types of dead and live loads.
    A good formwork should satisfy the following requirements:

    1. It should be rigidly constructed and efficiently propped and braced both horizontally and vertically, so as to retain its shape.
    2. The joints in the formwork should be tight against leakage of cement grout.
    3. Construction of formwork should permit removal of various parts in desired sequences without damage to the concrete.
    4. The material of the formwork should be cheap, easily available and should be suitable for reuse.
    5. The formwork should be set accurately to the desired line and levels should have plane surface.
    6. It should be as light as possible.
    7. The material of the formwork should not warp or get distorted when exposed to the elements.
    8. It should rest on firm base.

    Types of Formwork (Shuttering) for Concrete Construction:

    Timber Formwork:

    Timber for formwork should satisfy the following requirement:
    It should be
    1. well seasoned
    2. light in weight
    3. easily workable with nails without splitting
    4. free from loose knots
    Timber used for shuttering for exposed concrete work should have smooth and even surface on all faces which come in contact with concrete.

    Normal sizes of members for timber formwork:


    Sheeting for slabs, beam, column side and beam bottom
    25 mm to 40mm thick
    Joints, ledges
    50 x 70 mm to 50 x 150 mm
    Posts
    75 x 100mm to 100 x 100 mm


    Resin bonded plywood sheets are attached to timber frames to make up panels of required sizes. The cost of plywood formwork compares favourably with that of timber shuttering and it may even prove cheaper in certain cases in view of the following considerations:

    Plywood Formwork

    1. It is possible to have smooth finish in which case on cost in surface finishing is there.
    2. By use of large size panels it is possible to effect saving in the labour cost of fixing and dismantling.
    3. Number of reuses are more as compared with timber shuttering. For estimation purpose, number of reuses can be taken as 20 to 25.

    Steel Formwork

    This consist of panels fabricated out of thin steel plates stiffened along the edges by small steel angles. The panel units can be held together through the use of suitable clamps or bolts and nuts. The panels can be fabricated in large number in any desired modular shape or size. Steel forms are largely used in large projects or in situation where large number reuses of the shuttering is possible. This type of shuttering is considered most suitable for circular or curved structures.

    Steel forms compared with timber formwork:

    1. Steel forms are stronger, durable and have longer life than timber formwork and their reuses are more in number.
    2. Steel forms can be installed and dismantled with greater ease and speed.
    3. The quality of exposed concrete surface by using steel forms is good and such surfaces need no further treatment.
    4. Steel formwork does not absorb moisture from concrete.
    5. Steel formwork does not shrink or warp.

    Construction of Concrete formwork:

    This normally involves the following operations:
    1. Propping and centring
    2. Shuttering
    3. Provision of camber
    4. Cleaning and surface treatment

    Order and method of removing formwork:

    The sequence of orders and method of removal of formwork are as follows:
    1. Shuttering forming the vertical faces of walls, beams and column sides should be removed first as they bear no load but only retain the concrete.
    2. Shuttering forming soffit of slabs should be removed next.
    3. Shuttering forming soffit of beams, girders or other heavily loaded shuttering should be removed in the end.
    Rapid hardening cement, warm weather and light loading conditions allow early removal of formwork. The formwork should under no circumstances be allowed to be removed until all the concrete reaches strength of atleast twice the stresses to which the concrete may be subjected at the time of removal of formwork. All formworks should be eased gradually and carefully in order to prevent the load being suddenly transferred to concrete.
    Conventional column shuttering



    b. Casting of columns
    After ensuring the verticality and correct position of column’s shuttering the columns are casted .
    · Plumb is again checked after the casting as column shuttering displace a little by pouring
    Concrete pressure
    · Grade of concrete.
    · Nominal cover provided: 40mm